Welding of main circulation pipeline completed at 2nd power unit of Belarusian NPP
It took 70 days and this stage became a new benchmark for similar work at subsequent nuclear power units. Welding of a main circulation pipeline is given special attention to: the entire schedule of hydrotesting of the reactor unit is made based on the date of completion of this process.